Is this article helpful?

Complete the migration cutover

After the imported task has been reviewed, configured, and tested, complete the cutover from MOVEit Automation to Automate MFT.

  1. Disable the original task or schedule in MOVEit Automation.
  2. Verify that the original task cannot run automatically in MOVEit Automation.
  3. Open the imported task in Automate MFT.
  4. Confirm that all warnings, comments, schedules, endpoints, authentication methods, and task steps have been reviewed.
  5. Enable Auto-Run.
  6. Monitor the first production runs.
  7. Review task-run results and file activity.
  8. Confirm that files are not being processed by both MOVEit Automation and Automate MFT.